Skip to content
CapRadio

CapRadio

listen live donate
listen live donate
listen live
donate
  • News
    • News

    • State Government
    • Environment
    • Health Care
    • Race and Equity
    • Business
    • Arts and Lifestyle
    • Food and Sustainability
    • PolitiFact California
    News
    • News

    • State Government
    • Environment
    • Health Care
    • Race and Equity
    • Business
    • Arts and Lifestyle
    • Food and Sustainability
    • PolitiFact California
  • Music
    • Music

    • Classical
    • Jazz
    • Eclectic

    • Daily Playlist
    Music
    • Music

    • Classical
    • Jazz
    • Eclectic

    • Daily Playlist
  • Podcasts & Shows
  • Schedules
  • Events
  • Support
    • Support
    • Ways to support
    • Evergreen Donation
    • One-Time Donation
    • Corporate Sponsorship
    • Vehicle Donation
    • Stock Giving
    • Legacy Giving
    • Endowment Support
    • Members
    • Member Benefits
    • Member FAQ
    • Member Newsletter

    • Fund drives
    • Drawing Winners
    • Thank You Gifts
    Support
    • Support
    • Ways to support
    • Evergreen Donation
    • One-Time Donation
    • Corporate Sponsorship
    • Vehicle Donation
    • Stock Giving
    • Legacy Giving
    • Endowment Support
    • Members
    • Member Benefits
    • Member FAQ
    • Member Newsletter

    • Fund drives
    • Drawing Winners
    • Thank You Gifts
  • About
  • Close Menu
 We Get Support From:
Become a Supporter 
 We Get Support From:
Become a Supporter 

Rebuilding The Lake Oroville Spillways

  •  Bob Moffitt 
Wednesday, October 11, 2017 | Sacramento, CA
Bob Moffitt / Capital Public Radio

Crews set up concrete pours in a checkerboard pattern at Lake Oroville. Workers must wait four days for concrete to cure before pouring adjacent concrete. Millions of cubic feet of concrete will be poured before the project is completed.

Bob Moffitt / Capital Public Radio

In February, a huge hole opened in the Lake Oroville main spillway. The cause of the hole is still undetermined. The ensuing closure of the main gates and use of the emergency spillway for the first time ever caused damage to the hillside, erosion toward the spillway structure and thousands of people to evacuate. 

The California Department of Water Resources feared catastrophic flooding and chose to once again release water down the main spillway.

Fortunately, major flooding was averted.

State and federal agencies devised a plan to quickly repair or replace the structures at the lake.

Most, but not all, of the repair work is scheduled to end within a month. Here's how crews are working to rebuild the spillways.

A Spillway In Four Parts

Listen
/
Update RequiredTo play audio, update browser or Flash plugin.

 

Kiewit Construction says by the time construction on the main chute ends this year, a 3,000 ft ramp will connect the gates at the top to the energy diversion blocks at the bottom.

Even though concrete pours will stop Nov. 1 on the main spillway, more concrete will be required next year. 

The top 730 feet is the original chute and will remain for one more winter and will then be replaced.

Three new sections below are under construction. 

Section two measures 870 feet and includes the original damaged area.

Section three measures 1050 feet and includes the lower of the two significantly-damaged areas.

1003 17 bm Oroville spillway hole remains

About 500 feet remains between the bottom of section two and the top of section three. Bob Moffitt / Capital Public Radio News.

Section four is 350 feet long and includes the energy diffusion blocks at the bottom. Those blocks will be resurfaced next year.

Section three is covered in roller compacted concrete or RCC right now.

Although there is a gap of several inches between sections three and four, Jeff Petersen, who is the Oroville Project Leader, says it won't be there when the work is done.

"Anchors connect all that concrete so it's all anchored back down to the rock and the RCC will butt into that and tie in with more anchors. So, it just provides a real solid connection.

But it's a temporary fix.

"It will be a perfectly smooth." he says. "It will be smoother than what you see here because this isn't the final lift."

Section three will be topped with two-and-a half feet of rebar-enforced structural concrete next year.

The gap between sections three and four is nothing compared to the 500 feet of bare rock that is still exposed where the spillway originally gave way in February.

Crews are filling that void at five feet per day.

The Emergency Spillway

Listen
/
Update RequiredTo play audio, update browser or Flash plugin.

As water approached the emergency spillway at Lake Oroville in February, people began to realize that the emergency spillway ramp was nothing more than a dirt hillside.

That's when the concrete trucks started to make round-the-clock deliveries.

1003 17 bm Oroville emergency spillway

The Lake Oroville emergency spillway is 1450 feet long. Concrete and concrete-embedded rocks called riprap will remain this winter as crews build a cutoff wall below.  Bob Moffitt / Capital Public Radio

 

Petersen says that concrete will remain as a temporary splash pad if the emergency spillway is needed again this winter.

"The concrete you see down here was all placed in February during the event and we won't touch that."

They won't touch that...for now. A new landing pad is scheduled for next year.

Like the spillway, it will measure 1,450 feet long. The pad would have berms on each side, 10 feet tall and 15 feet wide, and would direct water to a low-lying area in the rock formation below and then to the diversion pool below that.

First, crews must drill 75 feet down into solid rock to create the forms for a cutoff wall.

Petersen says crews must create forms for the wall, "The starter wall is cast concrete and you can see the round indentations in it. That provides a guide, like a drill-bit guide for the three-foot-diameter drill to get in the right locations and the right alignment."

The cutoff wall could be complete by late December or early January.

1003 17 bm Oroville emergency spillway cutoff wall

Crews are building a cutoff wall as long as the 1,450-foot emergency spillway. While the main spillway measures 3,000 feet, the cutoff wall is being installed 732 feet below the emergency spillway. Bob Moffitt / Capital Public Radio

There is also a plan for a buttress that would be 10 feet wide and 30 feet tall and would be adjacent to the emergency spillway. The buttress is intended to support the emergency spillway.

There are no plans to build a complete concrete emergency chute similar to the main spillway.

Main Spillway Drainage

Listen
/
Update RequiredTo play audio, update browser or Flash plugin.

The old Lake Oroville main spillway and the new spillway both have the same enemy: water.

For every 30 feet of the new surface, there is a 6" drainage pipe four-to-13 feet below the surface. Petersen says new technology should prevent any water from getting through the concrete from the top.

"It flows from the middle out, the water does. If water went down through the slab, it would collect it. That's not likely because a new technology in this construction is the water-stop joint and you can see it in this white vinyl. That water stop is at every joint. So, water can't really get down there." 

1003 17 bm Oroville drainage

Workers at the Lake Oroville main spillway prepare the areas between concrete slabs to receive drainage pipes. Bob Moffitt / Capital Public Radio News

That's not to say water absolutely won't make it to the drains.

"Over time," Petersen says, "a slab separates or cracks or whatever happens to the concrete in the years ahead, the drainage system collects the water that goes through."

The new pipe is durable plastic and the California Department of Water Resources says there are more of them than were under the old spillway.

The pipe under the old spillway was made of clay.

When groundwater pushes its way up through cracks in the rock, Petersen says the drainage system can handle that too.

"The drainage system connects to the rock and the slab. So it would collect water coming up also, gets in the pipe, and goes back out to the sides, then those sides follow the chute walls and the water comes back into the chute."

1003 17 bm Oroville spillway side channel

The white pipes coming out of the drainage system will connect with pipes that will feed the water into the main spillway.  Bob Moffitt / Capital Public Radio

Fifty six piezometers are being placed all around the site at places selected by engineers to monitor water pressure under the concrete.

All told, there are about three miles of pipe under the spillway. 

Main Spillway Temporary Walls
Listen
/
Update RequiredTo play audio, update browser or Flash plugin.

Kiewit Construction is erecting 3,000 feet of walls on each side of the Lake Oroville main spillway.

The sections of walls are in various stages of completion. Some are finished. Others are wooden frames covered by wire mesh.

Petersen says the interior wall is a roller-compacted concrete that is finished with a type of concrete called shotcrete.

1003 17 bm Oroville spillway wall unfinished

Crews work on a slope of 4:1. They must erect scaffolding and a frame of wire and wood for the walls at the Oroville main spillway.  Bob Moffitt / Capital Public Radio News

"High air pressure blows it onto the wall. It's very similar to a swimming pool construction," he says."Then they just use a trowel finish with good piano wire guides to get the concrete to the smooth finish they want

He says the walls must allow water to flow with minimal resistance.

"This has to be what they call the high velocity concrete finish, so smoothness is very important. They don't want any turbulence on the water to cause extra erosion."

The California Department of Water Resources says the walls must be able to withstand 100,000 cfs traveling 78 mph.

1003 17 bm Oroville spillway wall finished

It's may appear rough, but this wall of finished shotcrete is smooth to the touch. Bob Moffitt / Capital Public Radio

Petersen says the temporary walls take two weeks to build.

Permanent walls that use rebar-enforced structural concrete take six months to build and the middle section of the spillway was only recently cleared to begin construction. That would have put wall construction into next April, well into the rainy season.

DWR says it has used the main spillway 26 times in the past 48 years.

Changing Materials

Listen
/
Update RequiredTo play audio, update browser or Flash plugin.

Crews in the mid 1960's were not using liquid nitrogen to make structural concrete for the Lake Oroville main spillway. But workers replacing the damaged spillway are.  

Petersen says this is not your grandfather's concrete. 

"This concrete with the chemicals we have now is actually called erosion-resistant concrete. And so, it holds up a lot better to erosion over time and this is the concrete that has the extreme temperature control. So, at the batch plant, we make it with ice. We cool it off with liquid nitrogen and then we bring it out here. It has to be 50 degrees on the grade."

It takes 28 days for it to cure and it must be cool and wet for 14 days.

1003 17 bm oroville spillway structural concrete
Leveling concrete cures as crews install rebar and epoxy-coated rebar above. The concrete and rebar combination at the Lake Oroville main spillway site is called “structural concrete.”  Bob Moffitt / Capital Public Radio

One section of the new spillway consists of a different type of concrete that allows heavy machinery to work on it immediately. A vibratory single-drum compaction roller helps jiggle it into a solid.

"It's not that liquid. Roller compacted concrete isn't liquid like you're used to seeing concrete come out of a concrete truck. It's damp. It really just looks like wet base rock. But, the fill feels like you're walking on Jell-O until it cures."

One other change compared to fifty years ago is how the concrete is poured.

Roller compacted concrete has no score lines or sections until the top ten feet.

And the erosion resistant structural concrete is poured in thirty-foot-wide squares parallel to the sides of the spillway. The original spillway was poured in a herringbone pattern.

DWR estimates the cost of the spillway projects at $275 million. The total recovery effort is estimated to cost about $500 million.


Follow us for more stories like this

CapRadio provides a trusted source of news because of you.  As a nonprofit organization, donations from people like you sustain the journalism that allows us to discover stories that are important to our audience. If you believe in what we do and support our mission, please donate today.

Donate Today  

    More about Oroville Dam

  • Oroville Dam

    Related Stories

  • Bob Moffitt / Capital Public Radio

    California Politicians Weigh In On Oroville Dam Report

    Tuesday, January 9, 2018
    California Assemblyman James Gallagher joins Insight to discuss the Oroville Dam crisis and how it was managed.
  • Bob Moffitt / Capital Public Radio

    Oroville Residents Blast State Over Dam Repairs

    Thursday, December 7, 2017
    Oroville residents vented decades of frustration with state water managers Wednesday, telling officials they have no credibility when they say hairline cracks in a newly rebuilt spillway are nothing to worry about.
  • Bob Moffitt / Capital Public Radio

    Oroville Dam Repair Costs Nearly Double To More Than $500 Million

    Thursday, October 19, 2017
    (AP) - California officials say repair costs at the Oroville Dam will be nearly double the original estimate of $275 million.

 Oroville DamOroville spillway

Bob Moffitt

Former Sacramento Region Reporter

Bob reported on all things northern California and Nevada. His coverage of police technology, local athletes, and the environment has won a regional Associated Press and several Edward R. Murrow awards.  Read Full Bio 

Sign up for ReCap and never miss the top stories

Delivered to your inbox every Friday.

 

Check out a sample ReCap newsletter.

Thanks for subscribing!

Thank you for signing up for the ReCap newsletter! We'll send you an email each Friday with the top stories from CapRadio.

Browse all newsletters

More Stories

Photo by Pablo Unzueta fro CalMatters

California workers can’t get timely hearings on wage theft claims. State orders audit.

March 23, 2023

Mario Tama/Getty Images

It's not just Adderall: The number of drugs in short supply rose by 30% last year

March 24, 2023

Julie Leopo/EdSource

California is preparing more credentialed teachers, but is it enough?

March 24, 2023

Most Viewed

State may scale down its new home loan program designed to assist first-time homebuyers

California coronavirus updates: The FDA may soon authorize another round of boosters for some individuals

California coronavirus updates: Americans' life expectancy has dropped to 76 years, second time in a row since pandemic

10 new California laws that go into effect in 2023

Need help for loved ones with severe mental health illness? California has a plan

We Get Support From:
Become a Supporter

Most Viewed

State may scale down its new home loan program designed to assist first-time homebuyers

California coronavirus updates: The FDA may soon authorize another round of boosters for some individuals

California coronavirus updates: Americans' life expectancy has dropped to 76 years, second time in a row since pandemic

10 new California laws that go into effect in 2023

Need help for loved ones with severe mental health illness? California has a plan

Back to Top

  • CapRadio

    7055 Folsom Boulevard
    Sacramento, CA 95826-2625

    •  
      (916) 278-8900
    •  
      (877) 480-5900
    •  Contact / Feedback
    •  Submit a Tip / Story Idea
  • About

    • Mission / Vision / Core Values
    • Stations & Coverage Map
    • Careers & Internships
    • Staff Directory
    • Board of Directors
    • Press
  • Listening Options

    • Mobile Apps
    • Smart Speakers
    • Podcasts & Shows
    • On-Air Schedules
    • Daily Playlist
    • Signal Status
  • Connect

    •  Facebook
    •  Twitter
    •  Instagram
    •  YouTube
  • Donate

  • Listen Live

  • Newsletters

CapRadio stations are licensed to California State University, Sacramento. © 2023, Capital Public Radio. All Rights Reserved. Privacy Policy | Website Feedback FCC Public Files: KXJZ KKTO KUOP KQNC KXPR KXSR KXJS. For assistance accessing our public files, please call 916-278-8900 or email us.