Oroville Dam Repair Costs Nearly Double To More Than $500 Million

Bob Moffitt / Capital Public Radio

Crews set up concrete pours in a checkerboard pattern at Lake Oroville. Workers must wait four days for concrete to cure before pouring adjacent concrete. Millions of cubic feet of concrete will be poured before the project is completed.

Bob Moffitt / Capital Public Radio

(AP) - California officials say repair costs at the Oroville Dam will be nearly double the original estimate of $275 million.

Department of Water Resources spokeswoman Erin Mellon said Thursday the contract with Kiewit Corp. at 770-foot Oroville Dam will grow to more than $500 million.

Kiewit project director Jeff Petersen said the project has required significantly more excavation and concrete than expected.

The main spillway and emergency spillway suffered significant damage during storms last February, prompting fears of massive flooding. Tens of thousands were evacuated but disaster was averted.

Petersen said the project is on schedule to finish pouring concrete on the main spillway by Nov. 1.